Two-storey extension estimate.
Two-storey extensions add significant floor area but bring extra complexity — structural steel, taller scaffolding, and coordinating finishes across two floors. This guide helps builders price the additional work accurately.
Authored by Alexandr Vreme & Maksym Vasylkov
Published — Next review
Who this guide is for
For builders and estimators pricing two-storey rear or side extensions. The extra storey adds structural, access, and programme complexity that single-storey experience alone does not fully prepare you for.
Information you need before pricing
In addition to the information required for a single-storey estimate, you will need:
- Staircase location and headroom — can a straight flight fit, or do you need a half-landing?
- First-floor joist spans — engineered joists or Posi-Struts may be needed for clear spans
- Steel transfer beams — typically 2–4 beams to support the first floor and roof loads
- Roof tile matching — finding like-for-like tiles for the extension roof
- Existing foundation capacity — deeper strip or piled foundations to carry additional storey loads
Extra items over a single-storey extension
- Structural engineer design and calculations for steelwork and foundations
- Steelwork — typically 2–4 steel beams with padstones and fire protection
- First-floor joists or engineered cassettes
- Staircase — supply and install, plus making good the ceiling below and any half-landing
- Additional first-floor plumbing and electrics
- Extra scaffolding height and loading for brick and materials at first-floor level
- Longer programme — typically 16–24 weeks versus 8–12 for single-storey
Typical cost breakdown
As a rough guide, the cost splits roughly:
- Ground floor works: ~55% of total cost
- First floor works: ~35% of total cost
- Roof works: ~10% of total cost
Commonly missed costs
- Temporary propping during steel installation — acrow props, needle beams, propping design
- Scaffold design certification for two-storey height
- Material hoisting — cranage or telehandler for steel beams and floor cassettes
- Longer prelims — extended site welfare, supervision, and hire costs over a 16–24 week programme
- Party wall awards for deeper foundations and steel beam bearing on shared walls
Miniature worked example
A 30 m² footprint two-storey rear extension with pitched roof:
- Ground floor (foundations, slab, walls, doors, finishes): £48,000
- First floor (steel, joists, walls, staircase, finishes): £38,000
- Preliminaries (scaffold, skip, welfare, supervision, design): £14,000
Total: approximately £100,000. For comparison, a single-storey extension of the same 30 m² footprint would be around £75,000. The two-storey premium reflects steelwork, staircase, and additional finishes.
Suitable output documents
- Detailed estimate with preliminaries separated from direct works
- Priced bill of quantities showing ground and first floor separately
- Programme of works with staged payment milestones
Questions to ask before pricing
- Has a structural engineer produced steel calculations yet?
- Where will the staircase land, and does it need a half-landing?
- What existing roof covering is on the house — can it be matched?
- Is there room for cranage or a telehandler on site?