New-build house estimate.

New-build estimating covers everything from groundworks through to completion. This guide explains the typical cost breakdown as a percentage of total build, what is commonly missed, and how to benchmark against industry norms.

Authored by Alexandr Vreme & Maksym Vasylkov
Published — Next review

Who this guide is for

This guide is for developers, self-builders, and contractors pricing a new-build dwelling from scratch. Whether you are building a single custom home or a small terrace, the percentage-based breakdown provides a reliable framework for early-stage budgeting before detailed quantities are available.

Information needed

To prepare an accurate new-build estimate, you will need:

  • Planning permission drawings and approved plans
  • Structural calculations — foundation design, steelwork, roof trusses
  • Ground conditions report — soil type, water table, bearing capacity
  • Utilities connection points — water, gas, electricity, drainage, broadband
  • NHBC or BLP warranty requirements and registration fees
  • Building regulations compliance strategy — fabric, ventilation, SAP calcs

Typical work breakdown

Industry benchmarks for a new-build house break down as follows (as a percentage of total build cost):

Substructure — foundations, ground floor slab, drainage12–18%
Superstructure frame — walls, floors, stairs20–25%
Roof — trusses, tiles, insulation, fascias10–12%
M&E — plumbing, heating, electrics, ventilation12–15%
Finishes — plaster, joinery, kitchen, bathrooms, decoration15–20%
External works — driveway, paths, landscaping, fencing8–12%
Preliminaries — site setup, welfare, management, scaffolding10–15%

Commonly missed costs

New-build projects carry several costs that first-time estimators often overlook:

  • Archaeological and ecology surveys required by planning conditions
  • S106 contributions — affordable housing, education, infrastructure payments
  • CIL (Community Infrastructure Levy) payments to the local authority
  • Attenuation tanks and sustainable drainage systems (SuDS)
  • Driveway and hardstanding — often budgeted separately but significant
  • Landscaping — turf, planting, shrubs, trees as required by planning
  • Boundary treatments — fencing, walls, gates
  • NHBC/BLP inspection fees throughout the build

Miniature worked example

A 100 m² three-bedroom new-build detached house:

Groundworks & foundations£25,000
Frame, roof, cladding£55,000
M&E (plumbing, electrics, heating, ventilation)£20,000
Finishes (plaster, joinery, kitchen, bathrooms, decor)£35,000
External works (driveway, paths, landscaping)£15,000
Preliminaries (scaffold, welfare, project management)£18,000
Total£168,000
Approx £1,680/m²

Excluding architect fees, planning costs, warranty registration, and VAT.

Questions to ask

  • Have all planning conditions been reviewed for additional survey requirements?
  • Is the foundation design suitable for the ground conditions identified in the site report?
  • Have utility connection charges been quoted by the relevant providers?
  • Does the budget include NHBC or BLP warranty fees and inspection costs?
  • Have S106 contributions and CIL payments been calculated and allowed for?
  • What is the provisional sum for external works — driveway, paths, landscaping?